A-level Paper 1, June 2018Markets and Business Behaviour
A-level Paper 1, June 2018, Q7
Evaluate the likely private costs and external costs involved in such major power station construction projects. Use an appropriate externalities diagram in your answer.
EssayEvaluateOptional25 marks
Context
In September 2016 the government approved the building of an £18 billion nuclear power station, Hinkley Point C, which will supply 7% of UK electricity for up to 60 years. The power station is funded by Chinese and French investment.
Original diagram required. See the original question paper for the diagram.